Member State Deliveries

Scoreboard of the Member States’ Article 17 reports

This page provides an overview on the state-of-play of the reporting in the form of two scoreboards (timeliness of the deliveries and quality of the data). Details of the criteria used are available here.

Timeliness of the report deliveries

Article 17 reports (1st delivery) were expected by 1 July 2013.
The scoreboard below shows the actual delivery dates.

The EEA and ETC/BD performed the Quality Assessment and Quality Control (QA/QC) on the data and gave feedback to Member States. After this, Member States submitted corrected reports (2nd delivery). Thus, a similar scoreboard for the 2nd delivery is made available.
The scoreboard indicating the quality of the reported data will be made on the basis of the second deliveries.

Member State Delivery date Link to 2nd Delivery
1st Delivery 2nd Delivery
CZ 24/06/2013 23/08/2013 gen spec hab all files
FI 26/06/2013 27/09/2013 gen spec hab all files
IE 27/06/2013 06/09/2013 gen spec hab all files
EE 28/06/2013 17/09/2013 gen spec hab all files
ES 28/06/2013 11/09/2013 gen spec hab all files
SE 28/06/2013 30/12/2013 gen spec hab all files
LV 28/06/2013 09/09/2013 gen spec hab all files
PT 28/06/2013 18/09/2013 gen spec hab all files
BE 01/07/2013 16/09/2013 gen spec hab all files
FR 03/07/2013 18/09/2013 gen spec hab all files
LU 05/07/2013 28/08/2013 gen spec hab all files
AT 12/07/2013 11/10/2013 gen spec hab all files
IT 19/07/2013 04/12/2013 gen spec hab all files
DK 24/07/2013 20/12/2013 gen spec hab all files
PL 29/07/2013 06/12/2013 gen spec hab all files
UK 31/07/2013 10/10/2013 gen spec hab all files
HU 01/08/2013 07/11/2013 gen spec hab all files
RO 06/09/2013 04/01/2014 gen spec hab all files
CY 24/09/2013 29/11/2013 gen spec hab all files
SI 02/10/2013 16/12/2013 gen spec hab all files
MT 02/10/2013 11/12/2013 gen spec hab all files
NL 08/10/2013 18/12/2013 gen spec hab all files
LT 09/10/2013 30/12/2013 gen spec hab all files
BG 15/10/2013 27/12/2013 gen spec hab all files
SK 29/10/2013 17/12/2013 gen spec hab all files
DE 15/11/2013 20/12/2013 gen spec hab all files
GR      

The criteria for assigning a smiley based on date of delivery is explained below.

1st delivery 2nd delivery
submitted by the deadline (1st July 2013) submitted by the deadline - i.e. six weeks after the feedback (Qa/Qc report)
delayed by less than one month submitted after the deadline, but before the cut-off date
delayed by more than one month submitted after the cut off-date or 2nd delivery not submitted